How is Low Volume Production (LVP) tooling different from development or production tooling?

Mould tool options which give flexibility for time versus cost......Injection Moulding

Introduction

When we talk about injection mould tooling, the big perceived barriers are usually cost, closely followed by lead time. If the part quantities are low then the amortised effect of the tooling is substantial. Thus to use injection moulding as a process, and to apply it to low volumes of parts, requires a different approach.

This is how we do it at Plunkett Associates:

Development Tooling

Prototype or development tooling is all about speed and how quickly moulded parts can be made available. In this scenario the toolmaker may employ a number of time saving options, for example the use of standardised bolsters, minimal cooling, or loose inserts. Textures may well be omitted, blanket tolerances applied, part marking ignored, recycling codes omitted etc. Whilst this may sound drastic, remember these are prototype parts and as such may have a short life.

Production ToolingAluminium Tooling

Production tooling on the other hand, is designed from the outset with a different driver, i.e. low cycle time. It is all about producing as many parts in the shortest mould press cycle as possible. That's because press time reflects on piece part price and hence final product price. All marking will have to conform to various standards, inserts will be automated and fitted with wear plates for maintenance and cooling optimised from a stability/cycle time perspective. Parts will be moulded in tens of thousands upwards.

Low Volume Production Tooling

Low Volume Production (LVP) tooling is a hybrid of both techniques and the exact configuration will be customised to the client/geometry/requirement.

Frequently, production quantities will be between hundreds and low thousands per annum. Cooling is thus about part stability and repeatability rather than cycle time.

Similarly lose inserts may still be a viable proposition especially if threaded inserts are also being utilised.

Standard bolsters (where the bolster remains the property of the toolmaker and the client only buys the inserts/ejector system) can be used. The client is the deciding factor. Where there is a requirement to be able to move the tools between moulders then this is not an ideal solution due to the need for a new bolster set to be created. However time and cost can be saved if this flexibility can be waived or deferred. In both cases the client owns the insert assembly.

As these are production parts, textures are usually a requirement albeit that they are often applied by blasting as opposed to EDM or chemical etching.

Part identification, recycling codes and date clocks can all be included if required.Injection Moulding Machine

Tool material is a function of quantity and material being moulded. Aluminium, so long as it is a suitable toolmaking grade, offers lowers costs, faster machining and the ability to mould tens of thousands of parts if required. For this reason it is frequently the material of choice for these applications.

As stated at the outset, these tools are hybrids, or customised to strip out unnecessary cost and lead time. Depending on what can be agreed, costs can be saved and the economics of small volumes improved, making injection moulding viable at surprising small quantities.

The result is a mould tool that reflects the requirement and opens up an exciting option to produce high quality, yet low volume components.

Associated pages:

Development Tooling

Prototype/Rapid Tooling

Bridge Tooling

Production Tooling

  • “Plunkett Associates have excellent breadth of experience, work with high quality partners and have a flexibility that we have found enables challenges to be met successfully, cost effectively and in a timely manner.”
    Nick Skaer, CEO, Orthox Ltd
  • Plunkett associates always find a solution. Whatever we need to prototype, they have a great grasp on the technologies available, costs and lead-times so we get the right solution tailored to the project needs. Have always delivered and never let us down.
    Naim Audio
  • “I can’t recommend Tim and his team highly enough. We ended up with a design which can be produced and assembled quickly, efficiently and reliably, in volumes that make sense”
    Simon Leggett, Director, Olivewood Technology
  • "Tim's experience, expertise and supplier base have been fundamental to us getting this project off the ground."
    Sam Pearce, Jelly Products Ltd
  • “We were really surprised at how quickly they turned round such a high quality prototype and the parts certainly proved their worth. They were of high enough quality to provide a fantastic visual representation and to undergo rigorous testing."
    Stuart Wilson, Design Director, TRT Lighting
  • “Accuracy, finish and delivery all first class.”
    Andrew Peters, JMDA Ltd
  • “We use Plunkett Associates because we want someone we can trust, that knows what they’re talking about, has all the contacts, will provide reliable advice and feedback and will get the right result for us.”
    Jim Copestick. Design Manager, Thorlux Lighting
  • “We always know exactly what we’re getting and we know we won’t be let down on quality, price or lead times.”
    Mark Williams, Research and Development Director, Johnson Safety Products
  • “Plunkett Associates truly offer a complete turnkey solution with Speed, Effectiveness and Precision.”
    David Harden, Director, Enica Ltd
  • “Kirintec were thrilled with Plunketts. They made a complex process simple and we were just amazed at the lead times achieved. Plus, every single deadline was met without any drama.”
    Penny While, Marketing Director, Kirintec
  • “Thanks to Plunkett Associates flexible, bespoke and cost effective service I was able to produce the objects that I had originally had in mind.”
    Simon Ryder, Artist
  • To create such a consistent quality finish in chrome was an amazing achievement and the prototypes really gave our stand the wow factor.
    James Clark, Group Commercial Director, The Airdri Group
  • Interestingly, people who look at it in its own right with little knowledge of what it does, just like it! It’s tactile and it looks good…
    Tim Collings, Operations Director, Troika Systems Ltd
  • "With their simple to understand language, willingness to go the extra mile and approachability, Plunkett Associates were a great partner for our company. We couldn’t be happier with the results of our project. (A working prototype that they got right first time, by the way). Thank you!"
    Carolina Ballon-Forrester, Director, Kittyrama Ltd
  • Plunkett Associates worked on the design and production of titanium frames for an artificial heart valve where precision and consistency was paramount. Communications were efficient and productive with concepts readily incorporated into the final design, and suggestions for improvements all highly appropriate. The quality of the end product was ideal and I have no doubt that I will use the advice and expertise of Plunkett Associates again.
    David Wheatley, Wheatley Research Ltd
  • “Thanks for the present that arrived this morning, as promised. Parts look first class, as always.”
    Jon Todd, Design Manager, PHS Group
  • “Plunkett Associates have a fantastic supply chain, work with all sorts of production processes and will always do their utmost to solve a problem.”
    Naim Audio
  • “ Plunketts developed a solution that met our precision requirements at a cost significantly lower than alternative manufacturing approaches we had investigated”
    Nick Skaer, CEO, Orthox Ltd
  • “Doing business with you has been an absolute pleasure. You have made my goals a reality. You have been patient, helpful and above all, responsive. Best service that I have experienced in ages. I consider Plunkett Associates to be an integral part of my business plan moving forward.”
    Jet Cooper, Sculptor
Related Processes

Injection Moulding

Produces production intent material properties. Injection Moulding is used for development as well as production parts.

more info

Read more expert articles in our FAQ section where we discuss topics on materials, methods and products.

Back to FAQs
  • “Plunkett Associates have excellent breadth of experience, work with high quality partners and have a flexibility that we have found enables challenges to be met successfully, cost effectively and in a timely manner.”
    Nick Skaer, CEO, Orthox Ltd
    Nick Skaer, CEO, Orthox Ltd
  • Plunkett associates always find a solution. Whatever we need to prototype, they have a great grasp on the technologies available, costs and lead-times so we get the right solution tailored to the project needs. Have always delivered and never let us down.
    Naim Audio
    Naim Audio
  • “I can’t recommend Tim and his team highly enough. We ended up with a design which can be produced and assembled quickly, efficiently and reliably, in volumes that make sense”
    Simon Leggett, Director, Olivewood Technology
    Simon Leggett, Director,  Olivewood Technology
  • "Tim's experience, expertise and supplier base have been fundamental to us getting this project off the ground."
    Sam Pearce, Jelly Products Ltd
    Sam Pearce, Jelly Products Ltd
  • “We were really surprised at how quickly they turned round such a high quality prototype and the parts certainly proved their worth. They were of high enough quality to provide a fantastic visual representation and to undergo rigorous testing."
    Stuart Wilson, Design Director, TRT Lighting
    Stuart Wilson, Design Director, TRT Lighting
  • “Accuracy, finish and delivery all first class.”
    Andrew Peters, JMDA Ltd
    Andrew Peters, JMDA Ltd
  • “We use Plunkett Associates because we want someone we can trust, that knows what they’re talking about, has all the contacts, will provide reliable advice and feedback and will get the right result for us.”
    Jim Copestick. Design Manager, Thorlux Lighting
    Jim Copestick. Design Manager, Thorlux Lighting
  • “We always know exactly what we’re getting and we know we won’t be let down on quality, price or lead times.”
    Mark Williams, Research and Development Director, Johnson Safety Products
    Mark Williams, Research and Development Director, Johnson Safety Products
  • “Plunkett Associates truly offer a complete turnkey solution with Speed, Effectiveness and Precision.”
    David Harden, Director, Enica Ltd
    David Harden, Director, Enica Ltd
  • “Kirintec were thrilled with Plunketts. They made a complex process simple and we were just amazed at the lead times achieved. Plus, every single deadline was met without any drama.”
    Penny While, Marketing Director, Kirintec
    Penny While, Marketing Director, Kirintec
  • “Thanks to Plunkett Associates flexible, bespoke and cost effective service I was able to produce the objects that I had originally had in mind.”
    Simon Ryder, Artist
    Simon Ryder, Artist
  • To create such a consistent quality finish in chrome was an amazing achievement and the prototypes really gave our stand the wow factor.
    James Clark, Group Commercial Director, The Airdri Group
    James Clark, Group Commercial Director, The Airdri Group
  • Interestingly, people who look at it in its own right with little knowledge of what it does, just like it! It’s tactile and it looks good…
    Tim Collings, Operations Director, Troika Systems Ltd
    Tim Collings, Operations Director, Troika Systems Ltd
  • "With their simple to understand language, willingness to go the extra mile and approachability, Plunkett Associates were a great partner for our company. We couldn’t be happier with the results of our project. (A working prototype that they got right first time, by the way). Thank you!"
    Carolina Ballon-Forrester, Director, Kittyrama Ltd
    Carolina Ballon-Forrester, Director, Kittyrama Ltd
  • Plunkett Associates worked on the design and production of titanium frames for an artificial heart valve where precision and consistency was paramount. Communications were efficient and productive with concepts readily incorporated into the final design, and suggestions for improvements all highly appropriate. The quality of the end product was ideal and I have no doubt that I will use the advice and expertise of Plunkett Associates again.
    David Wheatley, Wheatley Research Ltd
    David Wheatley, Wheatley Research Ltd
  • “Thanks for the present that arrived this morning, as promised. Parts look first class, as always.”
    Jon Todd, Design Manager, PHS Group
    Jon Todd, Design Manager, PHS Group
  • “Plunkett Associates have a fantastic supply chain, work with all sorts of production processes and will always do their utmost to solve a problem.”
    Naim Audio
    Naim Audio
  • “ Plunketts developed a solution that met our precision requirements at a cost significantly lower than alternative manufacturing approaches we had investigated”
    Nick Skaer, CEO, Orthox Ltd
    Nick Skaer, CEO, Orthox Ltd
  • “Doing business with you has been an absolute pleasure. You have made my goals a reality. You have been patient, helpful and above all, responsive. Best service that I have experienced in ages. I consider Plunkett Associates to be an integral part of my business plan moving forward.”
    Jet Cooper, Sculptor
    Jet Cooper, Sculptor